Date: Thu, 25 Nov 1999 10:56:26 +0100 > From: Fabio.Bossi@lnf.infn.it > To: BRESSANI@to.infn.it > Subject: LNF-SC Recommendations > > DAFNE > The Committee understands that the present limitation in the > machine's luminosity is mainly due to a 1.3 GHz mode in the kickers > which forces the use of a working point in the tunes plane far from > the one foreseen as optimal by the calculations. The Committee is > therefore looking forward to the insertion of the new kickers, > which should be delivered to the Lab by the fall of 1999, as an > important step in achieving a substantial increase in luminosity. > In the meanwhile the Committee endorses the proposal of the A.D. and > of the Directorate to rapidly set up a small committee of external > experts with the purpose of advising and helping the DAFNE crew > in the commissioning of the machine. > The Committee believes that, given the present situation, the best > running strategy is the following: > > end Nov. -end Dec. 1999: Stable run at the best achivable luminosity > with the main goal of delivering at least 100 nb^-1/day to KLOE. > At the same time collisions in the DEAR i.r. should also be > tried, with the purpose of letting DEAR study background > conditions with interacting beams. > If it turns out that stable colliding beams cannot be obtained in > both i.p. at the same time, two three-days periods should be > devoted to this studies, one at beginning and one at a later time > towards the end of the running period. > > Jan - end of Feb. 2000: Insertions of the new kickers. Start of the > installation of FINUDA, including installation of > the cryogenics lines, powering up of the magnet and measurement > and mapping of the magnetic field. > > March - July 2000: Resume of machine operations and colliding > beams for both KLOE and DEAR. The first two or three weeks of > this period should be devoted totally to machine studies, > while the remaining ones should be divided as follows: > three weeks of data taking for the experiments plus m.d. > and one week for continuing FINUDA installation as well > as for hardware interventions possibly needed by both > DAFNE and the other experiments. > > By the end of April 2000, the Committee will decide to keep or correct > this plan, according to the performances achieved by the machine. > > FINUDA > The Committee believes that today FINUDA is a well motivated community, > with many active young physicists fully devoted to the enterprise. The > status of preparation of the detectors is well advanced, for what concerns > the silicon detectors, the drift chambers, the straw tubes and the > scintillation counters. Most of the work that could possibly be done > in the assembly hall, was done. The Committee believes that now FINUDA > should be allowed to install as soon as possible the detectors in their > final position inside the magnet in order to proceed with the final alignment > and calibration. > With a complete detector they will also be able to progress in the testing > of the electronics and the data acquisition system; the collection of > cosmic ray data will allow them to check more thoroughly the reconstruction > programmes, the detector performance and the simulation software. > At the next meeting, the Committee would like to see a clear assessment > by FINUDA about the physics potentials that can be achieved in the case > they can collect 5 and 50 pb^-1. >