08:40
|
Welcome & Introduction
|
G.Dattoli
|
09:00
|
SPARC Project Status
|
L.Palumbo
|
09:30
|
Layout & alignment of linac
|
S.Tomassini
|
09:50
|
Installation & tests of the laser system
|
G.Gatti, S.Cialdi
|
10:20
|
Installation & tests of the RF system
|
R.Boni
|
10:40
|
Installation & tests of the low-level RF control
|
M.Bellaveglia
|
11:00
|
Coffee Break
|
|
11:20
|
Installation & tests of the RF gun & solenoid
|
F.Tazzioli
|
11:40
|
Solenoid beam dynamics simulations
|
C.Ronsivalle
|
12:00
|
Installation & tests of emittance-meter
|
L.Catani
|
12:30
|
Lunch
|
|
13:30
|
Visit to SPARC Hall
|
|
14:30
|
Status of the Undulator
|
M.Sassi
|
14:50
|
Undulator alignment & control
|
L.Semeraro
|
15:10
|
Undulator vacuum chamber & diagnostics
|
A.Doria
|
15:30
|
End
|
|
16:00
|
Closed Session
|
|
|
RF Milano Activity
|
M.Mauri
|
|
Lecce Activity
|
L.Cultrera
|
|
SPARC budget 2006
|
L.Palumbo
|
18:00
|
End
|
|