09:00 | Project Status | L.Palumbo |
09:30 | Schedule, Buildings | C.Sanelli |
10:00 | Layout and Mechanical Agreement | F.Sgamma |
11:15 | Beam Based Alignment | S.Guiducci, M.Ferrario |
12:00 | Status of Laser Pulse Shaping Tests | A.Ghigo, I.Boscolo |
12:40 | Control System | G.Di Pirro |
14:30 | Status of Undulator Design | F.Ciocci |
14:45 | Activities of the Roma2 Group | L.Catani |
15:10 | Practice at TTF-VUVFEL for Bunch Length Measurement at SPARC | E.Chiadroni |
15:40 | The SPARC Console System | E.Gabrielli |
Contributions |